Stop Saul-Epney Solar

Directions

Stop Saul-Epney Solar A Solar Farm, with BESS and Substation, is proposed for land between Epney and Upper Framilode. We are awaiting an actual planning application.

Everyone living in and around those areas will be affected.

05/10/2026

It beggars belief. Despite strong evidence as to why this development should not go ahead, the Inspecter has approved it!!

Summary

The Planning Inspector has today allowed the appeal for the Epney/Wheatenhurst solar farm, overturning Stroud District Council’s unanimous refusal. Permission is subject to 22 conditions.

The Inspector accepted that the grid connection compound would cause significant visual harm, but decided that the renewable energy and other benefits outweighed the harm. The proposed 28-metre connection mast has been removed from the scheme.

Of particular importance locally:

• Parkend Bridge’s 25-tonne limit must be respected, including the vehicle, fuel, driver and load. Vehicles must be weighed before crossing, with records kept. Any transformer, crane or other equipment that cannot comply must not cross the bridge.

• A detailed construction traffic plan must be approved before work starts, including arrangements to prevent two large vehicles meeting on Castle Lane or Parkend Bridge, protect footpaths and repair damage caused by construction traffic.

• The site is acknowledged to be functional floodplain. The Inspector accepted that the scheme would shut down during flooding, despite national policy saying essential infrastructure should remain operational. He gave that conflict little weight.

• Biodiversity, drainage, landscaping and construction safeguards require further approval. Construction hours are limited to 8am–6pm weekdays and 8am–1pm Saturdays, with no work on Sundays or bank holidays.

• The developer must provide arrangements for liaison with residents and the parish council, including handling complaints.

Please take this opportunity to get your view across to the people who make the planning decisions for our area.
02/07/2026

Please take this opportunity to get your view across to the people who make the planning decisions for our area.

Stroud District Council has launched an early consultation on a new Local Plan for the district, open from now until Sunday 9 August 2026 (11pm).

The new Local Plan will set out how and where growth should take place across the district over the next 15 to 20 years, balancing the need for new homes, jobs and infrastructure with the protection of the district’s valued environment and communities.

The government has set our new housing target - requiring us to plan for at least 846 new homes each year, a hugely challenging target - and our role as the Local Planning Authority is to seek to match that development to the places that work best for our communities. In doing so, this new Local Plan will play a vital role in shaping the future of Stroud district for the next generation.

We will always prioritise brownfield sites and have to work within the natural constraints of our district, including the flood plain and the Cotswold National Landscape. We also want to agree some core principles, as far as we can within the national framework, for what really good development looks like in our area.

This early consultation is about identifying those core principles, and the priorities, challenges and opportunities for the district. We want to hear from as many people as possible at this first stage so that local views help inform the plan from the outset. Please do get involved and give us your thoughts on your area and its future.

Find out more and take part:

www.stroud.gov.uk/environment/planning-and-building-control/planning-strategy/new-local-plan-2026/

01/06/2026

The appeal hearing for the solar farm is scheduled to take place on Wednesday 26th August 2026 from 10am in the Council Chamber at Ebley Mill.

The hearing is public and interested parties can attend to witness the procedure.

Any objectors wishing to speak must liaise with the planning inspectorate about the possibility of speaking during the hearing, as this is strictly at the Inspectors discretion.

11/05/2026

Only FIVE, 5, days left to submit your comments, it is really important that the Inspectors understand YOUR thoughts and how you view the installation of a solar farm between Epney and Saul.

The deadline for representations must be submitted by 11:59 pm on 20th May 2026. follow the link to submit your comments - https://appeal-planning-decision.service.gov.uk/comment-planning-appeal/enter-appeal-reference, don't forget to include the appeal red APPEAL 6007595 in all correspondence.

Alternatively, your comments can be sent to this address
Planning Inspectorate
The Planning Inspectorate
C/o QUADIENT
69 Buckingham Avenue
Slough
SL1 4PN

Please do not send them to Stroud District Council.

Six days remaining to comment on the planning appeal.

Thank you to everyone who has already submitted their views. There is still time for others to take part before the deadline on 20th May 2026.

Don’t forget to quote Appeal Ref: APPEAL 6007595.
https://appeal-planning-decision.service.gov.uk/comment-planning-appeal/enter-appeal-reference using their reference

Alternatively, your comments can be sent to directly to this address
Planning Inspectorate
The Planning Inspectorate
C/o QUADIENT
69 Buckingham Avenue
Slough
SL1 4PN

Seven days, one week, remains for residents to ensure their views are heard before the deadline of 11:59 pm on 20th May 2026.

There are now just EIGHT days remaining to have your say on the planning appeal.

The deadline for comments is 20th May 2026 at 11:59 pm.

Nine days left to submit comments - follow either the link below or the postal address to send your comments in. Don't forget to include the Inspectorates Appeal ref - APPEAL 6007595.

There are now 10, TEN, days left to submit comments to the appeal. Comments can be submitted up to 11:59 pm on 20th May 2026. The appeal hearing start date is confirmed as 17th June 2026,

Appeal Ref: S.26/010/APPREF
Appeal By : PACE Tribute Energy Ltd
Site: Land At Epney Framilode Gloucester Gloucestershire
Development: Installation of a solar photovoltaic (PV) farm with access tracks, fencing, landscape planting and other associated infrastructure.

PACE's Appeal Statement of Case is available to read on Stroud District Council's planning portal in the Appeals section.

Stroud District Council have sent the letters submitted on the original planning application to the Inspectorate but you can still submit more information.

There are 14 days to submit your comments on the Appeal by following the link

https://appeal-planning-decision.service.gov.uk/comment-planning-appeal/enter-appeal-reference using their reference APPEAL 6007595.

Alternatively, your comments can be sent to directly to this address
Planning Inspectorate
The Planning Inspectorate
C/o QUADIENT
69 Buckingham Avenue
Slough
SL1 4PN

You know this area, use your knowledge, state your case! 🙏

Firm deadline 20th May for any comments/objections