14/05/2026
Construction is moving forward
We continue our expansion and are steadily advancing the construction of the new Chemsys facility.
The project is already taking clear shape – key structural and engineering works have been completed:
- Foundations installed and main structural elements completed
- Reinforced concrete framework erected
- Floor slabs installed and roof structure works in progress
- External walls being installed using KINGSPAN panels
- Water supply, wastewater and rainwater systems installed
- Roof covering works planned in the near future
Each step brings us closer to a modern, efficient logistics and warehouse center with expanded capabilities.
Follow our progress – more updates coming soon!
[email protected] | www.chemsys.lt
--
Statybos sparčiai juda pirmyn
Tęsiame plėtrą ir nuosekliai įgyvendiname naujo Chemsys pastato statybos projektą.
Objektas jau įgauna aiškią formą – pagrindiniai konstrukciniai ir inžineriniai darbai jau atlikti:
Įrengti pamatai ir sumontuotos pagrindinės konstrukcijos
Pastatytas gelžbetoninis karkasas
Paklotos perdangos plokštės, vyksta stogo konstrukcijos įrengimo darbai
Montuojamos išorinės sienos iš KINGSPAN panelių
Įrengti vandentiekio, nuotekų ir lietaus nuvedimo tinklai
Artimiausiu metu planuojami stogo dengimo darbai
Kiekvienas etapas mus priartina prie modernaus, efektyvaus ir išplėstas galimybes suteikiančio logistikos bei sandėliavimo centro.
Sekite mūsų progresą – netrukus pasidalinsime dar daugiau naujienų!