30/04/2026
Due to power interruption closed po kami bukas, resume may 2, Saturday.
ππππππ ππ
πππππππππ πππππ ππππππππππππ
TO OUR VALUED MEMBER-CONSUMER-OWNERS:
SUBJECT: πππππππππ πππππ ππππππππππππ
DATE: May 1, 2026 (Friday)
TIME: 6:00AM to 6:00PM
ππππππππππ:
β’Power Transformers and Accessories Annual Preventive Maintenance
β’Correction of Hotspots
β’Right of Way Clearing of 69kV Sub T/L
β’Maintenance of Circuit Reclosers & Automatic Voltage Regulators (AVR)
ππ
π
πππππ πππππ:
β’Whole Municipalities of Bani and Agno
β’Part of Bolinao (Catuday, Zaragosa, Lambes, Sampaloc, Samng Norte, San Roque, Catungi, Samng Sur and Part of Tara & Tupa, Bolinao)
β’Part of Mabini (Cabanaetan, Mabini)
β’Parts of Alaminos City (Pogo, San Roque, San Antonio, San Jose, Landoc, Amangbangan, Tawin-Tawin, Polo, Inerangan, Alaminos City)
ππππππππ ππ ππ ππππππ:β’ β’69kV DS of Bani Substation
β’69kV SF6 CB
β’15kV VCB Feeders 1, 2, 3, 19, 20 & 21
We may energize the lines earlier than scheduled so PLEASE CONSIDER OUR LINES AND EQUIPMENT ENERGIZED AT ALL TIMES.