06/18/2026
The project resumed today after a short pause due to rain over the last couple of days. Progress has been made with the installation of rump rail posts and the pouring of concrete in the center and for equipment pads in the utility room. Soon, clear stone work will pick up again in the parlor, milk room, and utility room. The installation of the two remaining drain pans in the milk room is expected next week, paving the way for the in-floor heat installation. Parlor building is also set to start next week.