09/07/2024
Update 10/14 Hot water system replaced, new furnace installed and foundation repairs completed. Now we need to complete the parking lot and landscaping. If you can, please help us complete the tasks, we are close to full restoration. https://gofund.me/a21dd18a
Update 10/4 Work will start next week to replace the furnace and hot water systems, and work on repairing the foundations. Some work has also started on the parking lot. If you can, please help us complete the tasks. https://gofund.me/a21dd18a
Update 9/20 - With your kind generosity electric power and water restored today, the town approved the electric permit yesterday and the power was reconnected this morning. Propane is ready for connection when the hot water and HVAC is replaced. Your continued generosity is much needed and appreciated. https://gofund.me/a21dd18a
Update - Electric Contractor is now engaged and equipment ordered, parking lot is ready for millings. The HVAC and Plumbing contractor is ready to go. The building work for the foundation is in design.
If you have can, please help the rebuilding work on their gofundme page https://gofund.me/a21dd18a
==> To avoid confusion - there are 2 gofundme pages, one for the building, one for the restaurant. This go fundme will help fix the building which is not flood insured. The building needs to be fixed first before the restaurant can open.
Any donations gratefully received and many, many thanks to those who have helped so far.