03/13/2026
Been AWHILE!
Last update: roof on, water line trenched.
*4mo behind, 23% over budget. On it!*
here's our Update, final design and color scheme via Ai renders:
*Sitting room roof dented & incomplete, left zip tape under ridge vents, lawyer on it.
*Windows in.
*3 doors pend for dry-in.
*Plumbing elec framing insp passed.
*Elec boxes and wire installed.
*Plumbing roughed in, errors pend.
*Spray foam insulation underway.
*Framing caulked, windows, doors sealed.
*Bonus room framed as 2 bed, 1 storage, large bath and WIC w/Elec and plumb roughed in.
*Ceiling framing fixed. Truss st FP pends.
*Sheetrock ordered
*Foundation sealant ordered.
*Siding delivery 2 weeks out.
*Maintenence room built, insulated for sound, wired, water plant started.
*Rockwool in walls mstr &rec room.
*Int/ext stone blends, math & mason Id'd
*Painter on standby, paint id'd. See pics
*Cabinets, garage doors and flooring, plumbing fixtures identified.
*Great room FP plan id'd, see Ai pic.
Next week:
*Install any missing ceiling or corner nailers.
*Frame in door;end bdrm of bonus.
*Order 3 garage doors.
*Order gas line install
*Septic install.
*Start foundation sealant.
*Order concrete and block for ext stairs.
*Drywall starts Fri.
*crawlspace encapsulation/perimeter foam.
*Plumb pex into rockwool studbays. Route to mech room. (Solar radiant, sound proofed walls).